How Club Boards Can Avoid Cost Blowouts on Capital Projects

Noel Yaxley12 min read
club redevelopmentcost managementgovernancebudget
Featured image for How Club Boards Can Avoid Cost Blowouts on Capital Projects

Cost blowouts on club redevelopments are so common that many boards treat them as inevitable. They are not. The causes are predictable, and with the right approach, they are preventable.

Consider the scale of the problem. NSW clubs collectively spend approximately $920 million on capital works every year (ClubsNSW/Urbis, 2022). That is a significant pipeline of construction activity — and a significant volume of financial risk sitting with volunteer boards who may only oversee one or two major projects in their tenure. When 98% of Australian construction projects face delays (Buildern, 2026) and 74% of completed large and complex projects qualify as failures against their original targets (CIE), the odds are stacked against any board that does not take a disciplined approach to cost control.

Why club projects go over budget

The standard explanation is "construction costs increased." But that is a symptom, not a cause. The real reasons are almost always decisions made, or not made, before construction started.

1. The concept was never costed properly

Many clubs commission an architect to produce a concept design, present it to members for approval, and only then seek a detailed cost estimate. By this point, expectations are set, and the gap between ambition and budget becomes a political problem rather than a design one.

This is not a minor issue. Building material costs are now 47% above pre-pandemic levels (MBA/ABS, 2026). Cement products have risen 5.2% year-on-year, and while steel has eased slightly at -4.6% (MBA/ABS, 2026). The cumulative effect is that the architect's concept from twelve months ago may already be undercosted by the time the board presents it to members. A club that approves a $12 million project based on an uncosted concept could easily be looking at $14 million once a quantity surveyor gets involved. By then, the members have already voted.

Prevention: Commission an independent quantity surveyor to cost the concept at the earliest possible stage — before it is presented to members. If the numbers do not work, it is far cheaper to redesign than to manage a blowout. The QS estimate should include an escalation allowance that reflects the likely construction start date, not today's prices.

2. Staging was an afterthought

Maintaining club operations during construction is not optional, but it is expensive. Temporary walls, services diversions, phased demolition, and reduced access all add cost. When staging is only considered at the tender stage, these costs appear as surprises.

The financial impact of poor staging goes beyond direct construction costs. Weather delays alone increase project duration by 25.7% and costs by 23.8% on average (Buildern, 2026). When a club is operating at reduced capacity during construction, every week of delay is lost revenue from gaming, food, beverage, and functions. A club turning over $200,000 per week that drops to 60% capacity during construction is losing $80,000 per week. Add four months of weather and sequencing delays, which is not uncommon for a staged project, and that is $1.3 million in lost revenue that never appears in the construction budget but hits the club's bottom line just the same.

Prevention: Include staging as a design constraint from day one. The architect, quantity surveyor, and builder should all be briefing the board on staging costs as part of the independent feasibility assessment. Model the revenue impact of different staging sequences, not just the construction cost.

3. The scope changed after the contract was signed

Club boards are committees. Committees revisit decisions. Every scope change during construction triggers a variation — a formal change to the contract that almost always costs more than the original scope item would have.

This is where club governance creates a particular risk. A board of seven or nine directors, each with different priorities and constituent pressures, can generate a steady stream of "small" changes that individually seem reasonable but collectively erode the budget. A new finish in the lounge. An upgraded kitchen exhaust. An additional cool room. Each variation carries not just the direct cost of the work, but a margin for the builder, potential programme impact, and design fees for the architect and engineer to document the change. Industry data shows that disputes, many of which originate from poorly managed variations, absorb 2.6% of total project costs in Australian construction (Allens, 2022). On a $15 million project, that is $390,000 in avoidable cost.

Prevention: Implement a formal change management process. Every proposed change should be assessed for cost, programme, and approval impact before the board votes on it. The default position should be to hold the approved scope unless there is a compelling reason to change.

4. Variations were not independently assessed

Builders submit variation claims. Without independent assessment, the board has no way to verify whether the claimed amount is fair, whether the work was actually outside the original scope, or whether the programme impact is genuine.

This is not an accusation of dishonesty. Builders are entitled to recover costs for work outside their contract. But the assessment of what constitutes "extra" work and what it should cost is inherently a matter of interpretation. A builder who prices a variation using daywork rates when the work could have been priced competitively is not acting improperly. They are acting commercially. The problem is that without independent verification, the board has no basis to negotiate.

Labour costs have surged 25% above original estimates in many fixed-price contracts (industry analysis, 2025). Builders who are absorbing cost increases on their base scope have every commercial incentive to recover margin through variations. An independent assessment ensures the club pays a fair price — no more, no less.

Prevention: Have every variation assessed by an independent client-side advisor before it is approved. This single step can save clubs hundreds of thousands of dollars over the life of a project.

5. Contingency was spent too early

Contingency exists to cover genuine unknowns, not to fund scope changes. When contingency is treated as a slush fund for "nice to have" additions, the project runs out of buffer before construction is complete.

A well-managed project typically carries contingency of 5-10% depending on the procurement stage. On a $15 million club project, that is $750,000 to $1.5 million. It sounds like a large buffer, but it evaporates quickly if it is not governed. Consider that 3,217 construction companies collapsed in 2024, with a further 24% increase in insolvencies projected for 2025. If a key subcontractor fails mid-project, the cost to re-procure that work package will come from contingency. If that contingency has already been spent on upgraded floor tiles, the board has a serious problem.

Prevention: Ring-fence contingency with clear governance rules. Define what it can and cannot be used for, and require board approval for any drawdown. Track contingency as a separate line item in every project report.

What does a cost blowout actually look like?

To make this concrete, consider a hypothetical $15 million club redevelopment: a new gaming floor, refurbished lounge, upgraded kitchen, and new function space. This is a typical mid-range project for a suburban club in Sydney or regional NSW.

Original approved budget: $15.0M

Cost driverAmountRunning total
Approved budget$15.0M
Concept undercosted (no early QS, 8% gap)+$1.2M$16.2M
Staging costs not in original estimate+$600K$16.8M
Board-directed scope changes (6 variations)+$480K$17.3M
Builder variations (assessed without independent review)+$350K$17.6M
Weather and sequencing delays (4 months)+$380K$18.0M
Contingency exhausted early, further unknowns unfunded+$400K$18.4M
Lost revenue from extended programme (not in construction budget)+$520K$18.9M
Total outturn+$3.9M (26%)$18.9M

None of these individual items is outrageous. That is the problem. Each one is explainable in isolation. But the compounding effect turns a viable project into one that takes years for the club to recover from financially. A $3.9 million blowout on a club with $4 million in annual EBITDA means almost an extra year of earnings consumed, earnings that were supposed to fund the loan repayments the board approved based on the original $15 million budget.

This is not a theoretical exercise. Research on large Australian projects shows that those exceeding $200 million routinely blow budgets by 30% or more, with 77% delayed by over 40% of their original programme (ECU, 2024). Club projects are smaller, but the governance weaknesses that cause blowouts are the same, and often worse, because club boards lack the dedicated project teams that large infrastructure projects employ.

The role of independent oversight

Every one of these cost drivers can be managed with independent oversight. An advisor who reports to the board, not the architect, not the builder, provides the financial transparency that club governance requires.

This is not about adding cost. It is about preventing the costs that arise from decisions made without independent advice. Organisations with project management office (PMO) oversight achieve a 60% improvement in on-time and on-budget delivery, at a cost of roughly 5% of total portfolio value (PM Solutions, 2022). On a $15 million project, that is approximately $750,000 in advisory fees to avoid the kind of $3.9 million blowout illustrated above. The maths speaks for itself.

Independent oversight means:

  • Early cost assurance. A QS-backed budget before the concept goes to members, not after.
  • Staging and programme review. An independent assessment of the construction programme and staging sequence, identifying revenue risk before the contract is signed.
  • Change management. A formal process for evaluating scope changes, with independent cost and programme impact assessments presented to the board before decisions are made.
  • Variation assessment. Every builder variation reviewed by an independent advisor who understands the contract, the scope, and market rates.
  • Contingency governance. Monthly reporting on contingency status with clear recommendations on whether drawdown requests are appropriate.
  • Risk monitoring. Tracking contractor financial health, subcontractor performance, and programme risk. The kind of early warning system that gives a board time to act before problems become crises.

What should boards ask?

Before approving any capital project, every director should be able to answer these questions:

  1. Has the concept been independently costed by a quantity surveyor, including escalation to the expected construction start date?
  2. Is the staging strategy included in the budget, and has the revenue impact of reduced operations been modelled?
  3. What is the contingency amount, what percentage of the budget does it represent, and what are the governance rules for using it?
  4. Who will independently assess variations during construction, and what is their reporting line to the board?
  5. How will the board receive independent progress reports on cost, programme, and risk?

If any of these answers are unclear, the project is not ready for approval.

Frequently asked questions

How much does independent project oversight cost?

Typically 3-5% of the total project value, depending on scope and complexity. On a $15 million project, that is $450,000 to $750,000. Research shows that PMO oversight delivers a 60% improvement in on-time and on-budget delivery (PM Solutions, 2022). When the alternative is an unmanaged blowout of 20-30%, the cost of oversight is a fraction of the cost of not having it.

Our architect says they can manage costs. Why do we need a separate advisor?

Architects design buildings. They are not cost managers, and they have an inherent conflict of interest: their design is the thing being costed. An architect who tells you their $15 million design can be built for $15 million is giving you their opinion, not an independent cost assessment. A quantity surveyor or independent project manager provides the financial rigour that sits alongside the design expertise.

Can we just use a fixed-price contract to control costs?

A fixed-price contract transfers risk to the builder on paper. In practice, builders price that risk into the contract sum, and they recover margin through variations when the scope inevitably changes. With labour costs running 25% above estimates on many fixed-price contracts and 3,217 construction companies collapsing in 2024 alone, a fixed-price contract is only as reliable as the builder behind it. Independent oversight protects the club regardless of the contract structure.

When should we engage an independent advisor, before or after appointing the builder?

Before. The most valuable period for independent oversight is during feasibility and procurement, when the decisions that drive 80% of the final cost are being made. Engaging an advisor after the contract is signed is better than nothing, but it means the major cost commitments have already been locked in without independent scrutiny.

What if our project is only $3-5 million? Is oversight still worth it?

Yes. Smaller projects are often at greater risk because they receive less board attention and fewer resources. A 25% blowout on a $4 million project is $1 million — a material amount for any club. The scope of oversight can be scaled to match the project size and risk profile.


UpScale Project Management provides independent cost oversight for club redevelopments across NSW. Book a free consultation to discuss your club's project.

Noel Yaxley, Director of UpScale Project Management

Noel Yaxley

Director, UpScale Project Management

Architect-turned-project manager with experience across government infrastructure, commercial, and hospitality sectors. Noel founded UpScale PM to provide independent, client-side advisory for club boards navigating major redevelopment projects across NSW.